Rehabilitation of hospitals - Bamyan and Kabul

2006

Groupe de travail : Sandra d'Urzo ,


Objectives of the project : To prepare an architectural and technical proposal for the rehabilitation of the Bamyan and Kabul hospitals

Location : Kabul and Bamyan

Date of Commencement : November 2000

Duration : 3 weeks

Requested by : International Medical Aid

Methods of achievement :

1-Mission preparation at AMI

2-Mission in place, visit of the buildings, meetings and discussions with the Afghan personnel of the hospitals and the expatriates of AMI : a building site guide, a male nurse, a logistician/administrator, the doctor was not yet on the site

3-Elevation plan of the hospital, and the main building, pictures of the existing structure

4-Complete examination of the roofs, structures, door frames and networks

5-Definitions of the new functions and traffic organization according to the local cultural rules.

6-Revision of existing estimates prepared by the Afghan engineers

7-Drafting of a report of the mission to be presented to the expatriates at AMI

Local Partners :

Hospital of Bâmyân
The afghan engineers from « Solidarity « and AMI





Articles

Evaluation on East-Timor local construction technics

Evaluation mission - Local construction technic

Training Centre « Seyyed Djamaluddin » in Kaboul - 2 (Final)

One year later, the project is finished. The students started to take possession of the buildings from the very start of April. March was the (...)

Pakistan Earthquake Response in 2005

The efforts of A&D on the affected zones by the earthquake of magnitude 7.6 which struct Pakistan in October 2005. Thee epicentre of which (...)



ASFInt

Association membre du réseau Architecture sans Frontières International