Home > Our Work > Projects > Rehabilitation of hospitals - Bamyan and Kabul
Rehabilitation of hospitals - Bamyan and Kabul
Tuesday 3 October 2006, by
All the versions of this article: [English] [français]
Objectives of the project : To prepare an architectural and technical proposal for the rehabilitation of the Bamyan and Kabul hospitals
Location : Kabul and Bamyan
Date of Commencement : November 2000
Duration : 3 weeks
Requested by : International Medical Aid
Methods of achievement :
1-Mission preparation at AMI
2-Mission in place, visit of the buildings, meetings and discussions with the Afghan personnel of the hospitals and the expatriates of AMI: a building site guide, a male nurse, a logistician/administrator, the doctor was not yet on the site
3-Elevation plan of the hospital, and the main building, pictures of the existing structure
4-Complete examination of the roofs, structures, door frames and networks
5-Definitions of the new functions and traffic organization according to the local cultural rules.
6-Revision of existing estimates prepared by the Afghan engineers
7-Drafting of a report of the mission to be presented to the expatriates at AMI
Local Partners :
Hospital of Bâmyân
The afghan engineers from « Solidarity « and AMI